Bridge reconstruction estimated at $4.3 to $5.2 billion
Bridge reconstruction estimated at $4.3–$5.2 billion by Maryland Transportation Authority.
Event / Disaster
Maryland reached a settlement with the owner and operator of the M/V Dali cargo ship over the March 2024 Francis Scott Key Bridge collapse that killed six workers and caused major port disruption. Bridge reconstruction is estimated at $4.3-5.2 billion with completion expected in late 2030.
2026-08-19 to 2026-11-16 · UTC publication dates
Coverage begins 10 Apr, 01:37 UTC
Follow the documented timeline or explore the related reporting.
The state of Maryland filed claims in federal court in Maryland in September 2024 alleging that the Francis Scott Key Bridge disaster was the result of negligence, mismanagement, and reckless operation of a vessel that was not seaworthy and should never have left port. The state sought damages for bridge destruction, environmental harm to the Patapsco River, lost revenues, and wide-ranging economic losses.
The collapse of the Francis Scott Key Bridge resulted in the deaths of six men on a road crew who were filling potholes during an overnight shift. The bridge, a 1.6-mile steel span that opened to traffic in 1977, was a vital piece of transportation infrastructure for Baltimore and its port operations.
The M/V Dali, a massive cargo ship operated by Synergy Marine Pte Ltd and owned by Grace Ocean Private Limited, crashed into the Francis Scott Key Bridge in Baltimore on March 26, 2024. The ship was leaving Baltimore bound for Sri Lanka when its steering failed due to a power loss, causing it to collide with the bridge.
The Maryland Transportation Authority estimated the cost of constructing a replacement Francis Scott Key Bridge at between $4.3 billion and $5.2 billion, with an anticipated open-to-traffic date in late 2030.
The settlement between Maryland and the M/V Dali owner and operator does not resolve any claims the state may have against Hyundai, the shipbuilder of the vessel.
The collapse of the Francis Scott Key Bridge brought shipping at the Port of Baltimore to a complete halt. The disaster disrupted the livelihoods of thousands of workers, rerouted traffic through surrounding communities, and triggered economic ripple effects still being felt across Maryland.
Maryland reached a settlement in principle with Grace Ocean Private Limited and Synergy Marine Pte Ltd, the owner and operator of the M/V Dali cargo ship. The settlement resolves a portion of the state's claims arising from the ship's March 26, 2024 crash into the Francis Scott Key Bridge. Attorney General Anthony Brown announced the settlement on Thursday, April 10, 2026.
Bridge reconstruction estimated at $4.3–$5.2 billion by Maryland Transportation Authority.
Maryland settles with ship operator; Hyundai shipbuilder claims remain unresolved.
Cargo ship collision causes Baltimore bridge collapse, killing six workers.